OUTLINE DESCRIPTION OF FACILITY IMPROVEMENT MEASURES
Lisbon Town
Office
FIM- 1 Lighting
The
majority of the lighting scope is replacing linear T8 fluorescent fixtures with
newer generation more efficient lamps, while also replacing the ballasts with
new low powered ballasts. LED lighting
is also being installed in certain locations (mostly exterior and recessed can
lighting fixtures). There will be wall mounted occupancy sensors also installed
and where applicable vending misers to be installed on the current snack
machines.
FIM-2 Building Envelope
Scope of Work:
6 Single
Commercial Doors to be weather-stripped
2 Double
Commercial Doors to be weather-stripped
2 Roll-Up
Garage Doors to be weather-stripped, 68 linear feet
Note:
Building currently has an incomplete air-barrier, poly sheathing with
fiberglass batt and blown fiberglass above to a thickness of 3’ in most
locations
FIM-3 Water Conservation
Scope of Work:
Bathroom
fixtures offer good water saving opportunities because many of these fixtures
can be retrofit to reduce the amount of water consumed per flush (toilets and
urinals) or per minute of use (sinks and showers). Reducing sink and shower
water usage also saves the thermal energy used to make hot water
Domestic Fixture Quantities
Building\Total
|
Existing Fixture Quantity
|
Proposed Fixture Quantity
|
|||||||
Toilet
|
Urinal
|
Sink
|
Shower
|
Toilet
|
Urinal
|
Sink
|
Shower
|
||
|
|
|
|
|
|
|
|
|
|
Lisbon Town
Offices
|
12
|
2
|
11
|
2
|
2
|
2
|
11
|
-
|
|
FIM 3- Automation Enhancements
The Scope of this measure is that a new direct
digital control system be installed to provide automatic control to the 4
existing AHU’s and HW system pump. The new system will improve the
building engineer's ability to maintain comfort for the occupants and
staff. The following summarizes the building automation system controls:
·
The heating hot water pumps and the boilers will
be enabled and disabled based on the demand for heating. The operation of
the pumps will be proofed and alarmed when failure occurs. In the heating
plant, the boilers will be sequenced to maintain a hot water supply temperature
reset by outside air temperature.
·
Implement HW reset programming
·
The optimal start/stop and scheduling programming
will be incorporated into all the systems. These schedules will be
software adjustable, via a web based portal so that the engineer can adjust the
schedule to the changing needs of the building through the central operator
station.
·
This new controller would require an IP address
and network Jack, by owner.
·
Includes installation of Boiler isolation valves
to separate the boiler circuits.
·
This measure also includes on-site training for
the Building Engineers
FIM-4 Roof Replacement
The scope of this measure is to
replacement of the valleys using the following specification:
·
All work will be completed in accordance with
applicable OSHA safety standards.
·
Mobilize for
project in area shown on enclosed roof drawing (see exclusions).
·
Remove the
existing shingles 6’ wide in all highlighted valleys.
·
Install a
fiberglass-reinforced underlayment over the exposed deck.
·
Install new
3’ wide metal in the valleys.
·
Strip in new
valley metal with 6” ice and water shield.
·
Install new
shingles to achieve open valleys as required (shingle color to match existing
shingles as closely as possible).
Lisbon Library
FIM- 1 Lighting
The
majority of the lighting scope is replacing the current T12 and linear T8
fluorescent fixtures with newer generation more efficient lamps, while also
replacing the ballasts with new low powered ballasts. LED lighting is also being installed in certain
locations (mostly exterior and recessed can lighting fixtures). Wall mounted
occupancy sensors will also be installed.
FIM-2 Building Envelope
Scope of Work:
3 Single
Commercial Doors to be weather-stripped
3 Windows
to be caulked at perimeters, 58 linear, remaining original windows
12” Diameter
gravity vent in skylight should be sealed if not currently sealed, roof was not
accessible
Note:
Northwest corner of the roof requires drip edge and fascia replacement,
to avoid further water damage to structure.
FIM 3 – Water
Conservation
Scope
of work:
Bathroom
fixtures offer good water saving opportunities because many of these fixtures
can be retrofit to reduce the amount of water consumed per flush (toilets and
urinals) or per minute of use (sinks and showers). Reducing sink and shower water
usage also saves the thermal energy used to make hot water
Domestic Fixture Quantities
Building\Total
|
Existing Fixture Quantity
|
Proposed Fixture Quantity
|
|||||||
Toilet
|
Urinal
|
Sink
|
Shower
|
Toilet
|
Urinal
|
Sink
|
Shower
|
||
|
|
|
|
|
|
|
|
|
|
Lisbon Library
|
2
|
-
|
2
|
-
|
2
|
-
|
2
|
-
|
|
FIM- 4 Programmable Thermostats
The Scope of this measure is to replace the
existing thermostats with programmable thermostats with day/night scheduling.
This will set back the building during unoccupied heating and only heat based
on occupancy.
FIM-5 Roof Replacements
The scope of this measure is to completely replace
the existing roofing materials with a fully-warranted, insulated membrane roof
system using the following specification:
·
All work will be completed in accordance with
applicable OSHA safety standards.
·
Mobilize for
project in area shown on enclosed roof drawing (see exclusions).
·
Remove the
existing roofing materials down to the deck.
·
Remove
existing skylight and install new wooden deck in area (interior work by
others).
·
Install new
wooden nailers at perimeters as required.
·
Install one
layer of 2” polyisocyanurate insulation, mechanically fastened into the deck
with roof system manufacturer approved screws and plates.
·
Fully adhere
a .060” EPDM membrane, manufactured by Carlisle SynTec or Firestone Building Products,
to the new insulation.
·
Install new 24 gauge steel edge detail at all
perimeters (color by owner).
·
Install new
flashings along all walls and at all roof penetrations per manufacturer's
specifications.
·
Remove and
replace siding, as required, to install new flashings along walls.
·
Install new
vent stack boot at each existing vent stack.
·
Install new
scupper and open faced downspout.
·
This work
includes a 15-year limited membrane system warranty from the manufacturer.
MTM Center
FIM- 1 Lighting
The
majority of the lighting scope is replacing linear T8 fluorescent fixtures with
newer generation more efficient lamps, while also replacing the ballasts with
new low powered ballasts. LED lighting
is also being installed in certain locations (mostly exterior and recessed can
lighting fixtures). There will be wall mounted occupancy sensors also installed
and where applicable vending misers to be installed on the current snack
machines.
FIM-2 Building Envelope
Scope of Work:
4 Single
Commercial Doors to be weather-stripped
2 Double
Commercial Interior Doors to be weather-stripped
20 Beam
pockets to be sealed in gymnasium (10 per side)
Note:
Building currently receives grants yearly for window replacement. With the current grant estimate all windows
should be replaced in the building within the next 7 years. Gymnasium windows and doors are scheduled for
replacement in the Spring of 2014.
FIM 3 – Water Conservation
Scope
of work:
Bathroom
fixtures offer good water saving opportunities because many of these fixtures
can be retrofit to reduce the amount of water consumed per flush (toilets and
urinals) or per minute of use (sinks and showers). Reducing sink and shower
water usage also saves the thermal energy used to make hot water
Domestic Fixture Quantities
Building\Total
|
Existing Fixture Quantity
|
Proposed Fixture Quantity
|
|||||||
Toilet
|
Urinal
|
Sink
|
Shower
|
Toilet
|
Urinal
|
Sink
|
Shower
|
||
|
|
|
|
|
|
|
|
|
|
MTM Community
Center
|
12
|
1
|
10
|
-
|
10
|
1
|
10
|
-
|
|
FIM-4 Piping Insulation (distribution
improvements)
The scope of this measure is to add insulation to
the piping system at the MTM center. Some
of the energy in a building’s heating distribution system is wasted through
radiant thermal energy loss from a wide range of sources, including steam or
hot water piping. Escaping heat can lead to uncomfortable temperatures in
machine rooms and hallways or unnecessary heating of crawl space. Installing insulation to bare piping in these
areas conserves energy and reduces costs.
FIM-5 Burner Replacement/ Natural Gas
Conversion
The
scope for this measure will be to replacing the existing burner on the Buderus
boiler with a Riello G900 Gas On-Off burner to convert the system to natural
gas. To complete this conversion there will be some necessary code enhancements
listed below:
o
Add
combustion air- there is currently none
o
Upgrade
the backflow preventer
o
Update
the double acting barometric damper for natural gas
FIM-6 Automation Enhancements
Siemens recommends that a new direct digital
control system be installed to provide automatic control to the boiler plant,
pumps and domestic HW system pump. The new system will improve the building
engineer's ability to maintain comfort for the occupants and staff. The
following summarizes the building automation system controls:
·
The heating hot water pumps and the boilers will
be enabled and disabled based on the demand for heating. The operation of
the pumps will be proofed and alarmed when failure occurs. In the heating
plant, the boilers will be sequenced to maintain a hot water supply temperature
reset by outside air temperature.
·
Implement HW reset programming
·
The optimal start/stop and scheduling programming
will be incorporated into all the systems. These schedules will be
software adjustable, via a web based portal so that the engineer can adjust the
schedule to the changing needs of the building through the central operator
station.
·
This new controller would require an IP address
and network Jack, by owner.
·
Includes installation of Boiler isolation valves
to separate the boiler circuits.
·
This measure also includes on-site training for
the Building Engineers
FIM 7- Windows and Siding
The scope of this
measure is to install new windows and siding at the Lisbon MTM center. It will
include the following:
Main Building:
·
Remove
1,650 square feet of glass block walls and disposal
·
Infill
openings with framing, R-25 insulation, exterior sheating and drywall on
interior
·
Provide
and install double hung window units to match existing
·
Install
new vinyl siding and vinyl soffit to match existing
·
Install
new aluminum coil trip to match existing
Vestibule area:
·
Remove
wood panels and glass block walls in four areas
·
Remove
old steel framed windows; repair mortar as necessary; infill openings with
similar framing, siding and trim as above
·
Provide
Harvey vinyl windows to match existing
·
Insulate
wall sections; install 5/8 drywall; tape, sand and prime dry wall.
Lisbon Falls
Fire
FIM- 1 Lighting
The
majority of the lighting scope is replacing the current T12 and linear T8
fluorescent fixtures with newer generation more efficient lamps, while also
replacing the ballasts with new low powered ballasts. LED lighting is also being installed in
certain locations (mostly exterior and recessed can lighting fixtures). There
will be wall mounted occupancy sensors also installed and where applicable
vending misers to be installed on the current snack machines.
FIM-2 Building Envelope
Scope of Work:
2 Single
Commercial Doors to be weather-stripped
1 Double
Commercial Interior Door to be weather-stripped, to the ventilated hose tower
3 Overhead
Garage Doors to be weather-stripped, 136 linear feet
110’ Ceiling
caulking in rear compressor room, gypsum board joints
40’ Air-Sealing
at soffit joint above garage doors
FIM 3 – Water
Conservation
Scope
of work:
Bathroom
fixtures offer good water saving opportunities because many of these fixtures
can be retrofit to reduce the amount of water consumed per flush (toilets and
urinals) or per minute of use (sinks and showers). Reducing sink and shower
water usage also saves the thermal energy used to make hot water
Domestic Fixture
Quantities
Building\Total
|
Existing Fixture
Quantity
|
Proposed Fixture
Quantity
|
|||||||
Toilet
|
Urinal
|
Sink
|
Shower
|
Toilet
|
Urinal
|
Sink
|
Shower
|
||
|
|
|
|
|
|
|
|
|
|
Lisbon Falls
Fire Company
|
2
|
1
|
3
|
-
|
-
|
-
|
3
|
-
|
|
FIM 4- Programmable Thermostats
The Scope of this measure is to replace the
existing thermostats with programmable thermostats with day/night scheduling.
This will set back the building during unoccupied heating and only heat based
on occupancy. Programmable thermostats allow for a building to setback based on
zone occupancy as well as time of day. This will allow for energy savings in
areas that are intended for different purposes of operation throughout the
building.
ET Smith Hose
Company
FIM- 1 Lighting
The
majority of the lighting scope is replacing the current T12 and linear T8
fluorescent fixtures with newer generation more efficient lamps, while also
replacing the ballasts with new low powered ballasts. LED lighting is also being installed in
certain locations (mostly exterior and recessed can lighting fixtures).
FIM-2 Building Envelope
Scope of Work:
2 Single
Commercial Doors to be weather-stripped
4 Overhead
Garage Doors to be weather-stripped, 192 linear feet
858 Square
feet of 1” polyiso to be installed to the underside of the ceiling joists above
the drop tile ceiling, to complete the air barrier in the gathering room
portion of the building
FIM-3 Water
Conservation Measures:
Bathroom
fixtures offer good water saving opportunities because many of these fixtures
can be retrofit to reduce the amount of water consumed per flush (toilets and
urinals) or per minute of use (sinks and showers). Reducing sink and shower
water usage also saves the thermal energy used to make hot water
Domestic Fixture
Quantities
Building\Total
|
Existing Fixture
Quantity
|
Proposed Fixture
Quantity
|
|||||||
Toilet
|
Urinal
|
Sink
|
Shower
|
Toilet
|
Urinal
|
Sink
|
Shower
|
||
|
|
|
|
|
|
|
|
|
|
Lisbon Waste
Water Treatment Facility
|
3
|
-
|
3
|
1
|
3
|
-
|
3
|
1
|
|
FIM 4- Programmable Thermostats
The Scope of this measure is to replace the
existing thermostats with programmable thermostats with day/night scheduling.
This will set back the building during unoccupied heating and only heat based
on occupancy. Programmable thermostats allow for a building to setback based on
zone occupancy as well as time of day. This will allow for energy savings in
areas that are intended for different purposes of operation throughout the
building.
Transfer
Station
FIM- 1 Lighting
The
majority of the lighting scope is replacing the current T12 and linear T8
fluorescent fixtures with newer generation more efficient lamps, while also
replacing the ballasts with new low powered ballasts. LED lighting is also being installed in certain
locations (mostly exterior and recessed can lighting fixtures).
FIM-2 Building Envelope
Scope of Work:
1 Single Commercial Door to be weather-stripped, located in
trailer bay
1 Single
Commercial Door to be weather-stripped, located at the top of the stairwell
between the sorting bay and the trailer bay below
2 Overhead
Garage Doors to be weather-stripped, located in trailer bay, 112 linear feet
WWTP
FIM- 1 Lighting
The
majority of the lighting scope is replacing the current T12 and linear T8
fluorescent fixtures with newer generation more efficient lamps, while also
replacing the ballasts with new low powered ballasts. LED lighting is also being installed in
certain locations (mostly exterior and recessed can lighting fixtures). There
will be wall mounted occupancy sensors also installed and where applicable
vending misers to be installed on the current snack machines.
FIM-2 Building Envelope
Scope of Work:
Administration
5 Single
Commercial Doors to be weather-stripped
1 Double Commercial
Door to be weather-stripped
2 Overhead
Garage Doors to be caulked at perimeters (tops and sides), 64 linear feet
Head Works
2 Single
Commercial Doors to be weather-stripped
2 Overhead
Garage Doors to be weather-stripped, 64 linear feet
Maintenance Garage
2 Single
Commercial Doors to be weather-stripped
1 Double
Commercial Door to be weather-stripped
2 Overhead
Garage Doors to be weather-stripped, 104 linear feet
Dewatering Building
2 Single
Commercial Interior Doors to be weather-stripped
1 Double
Commercial Door to be weather-stripped
3 Roof Top
Ventilators to be opened, dampers lubricated and perimeters sealed, 12 linear
feet
2 Roll-Up
Garage Doors to be weather-stripped, 96 linear feet
National Guard Building
1 Single Commercial
Door to be weather-stripped
1
Overhead
Garage Door to be weather-stripped, 48 linear feet
FIM-3 Water
Conservation Measures:
Bathroom
fixtures offer good water saving opportunities because many of these fixtures
can be retrofit to reduce the amount of water consumed per flush (toilets and
urinals) or per minute of use (sinks and showers). Reducing sink and shower
water usage also saves the thermal energy used to make hot water
Domestic Fixture
Quantities
Building\Total
|
Existing Fixture
Quantity
|
Proposed Fixture
Quantity
|
|||||||
Toilet
|
Urinal
|
Sink
|
Shower
|
Toilet
|
Urinal
|
Sink
|
Shower
|
||
|
|
|
|
|
|
|
|
|
|
Lisbon Waste
Water Treatment Facility
|
3
|
-
|
3
|
1
|
3
|
-
|
3
|
1
|
|
FIM-5 Boiler Replacement/ Oil to LP
conversion
The scope for this measure is to replace the old
inefficient boilers at the office/lab building and the dewatering building to a
higher efficiency Buderus LP fired boiler. With these boiler replacements the
fuel source will be converted from Oil to LP gas.
FIm-6 Roof Replacement
The scope of this measure is to completely replace
the existing roofing materials with a fully-warranted, insulated membrane roof
system using the following specification:
·
All work will be completed in accordance with
applicable OSHA safety standards.
·
Mobilize for project in area shown on enclosed roof
drawing (see exclusions).
·
Remove the existing roofing materials down to the
deck. Install new wooden nailers at
perimeters as required.
No comments:
Post a Comment